No part of the log shall be wasted

This is almost an 11th commandment for people in the timber trade and it’s as important to Ransfords as anyone. The more material we recover from every tree felled the more efficient we are and the more competitive we can be. This short clip shows small diameter round wood (the thinner part at the top… Read more »

An astonishing transformation

These two aerial view of our Bishop’s Castle sawmill were taken about 50 years apart in the 1960’s and earlier this year. We’ve circled two points common to each to help you get orientated. They’re about all that remain of the original buildings. The rest in the modern picture is the result of well over… Read more »

Noise reduction on the M1

This picture shows our Noisewall single side reflective panels currently being installed by Littlewood Fencing on the M1 in the East Midlands between Junction 23A and 25. This huge project is one by Costain Galliford Try Construction to convert this stretch of road into a Safe Motorway. The re-purposing of the hard shoulder to take running traffic of all sizes… Read more »

The new Timber Treatment Centre from the air

When the autoclave was craned into our new Timber Treatment Centre last week it was quite spectacular: a crane rated  with a lifting capacity of 400 tons hoisting a 52 ton object through the building frame and placing it exactly in position 16 metres away. Hats off to Sam Cook of Tremio Aerial Photography who flew the… Read more »

Big lifts, with more to come

Nine weeks almost to the day since the first structural steel arrived on site the huge tanks which will store the chemicals used in our new Timber Treatment Centre have been hoisted into place. Next to go in will be the massive autoclave, the vessel into which the timber is placed for treatment under extremely high pressure. We’ll… Read more »

A hive of concrete pouring activity

This is the scene at our new Timber Treatment Centre today as the mixer wagons arrive to pour the concrete floor. It’s a pivotal moment in the construction: once the floor is set we can get on with the process of installing the autoclave, other equipment and the services which will make this one of the… Read more »

First structural steel arriving for our new treatment plant

With any building project there seems to be a long gap between the first idea and having anything on the ground to show for it. Our new treatment plant, which has been months in the planning, is no exception so it was great to see the first structural steels arrive on site. The new plant, which… Read more »